An update on the construction progress of LAVIQ Sukhumvit 57 for Q1/2018. The project was undergoing floor and structural column reinforcement, structural concrete pouring, elevator wall works, 5th-floor works, and stair works, with actual progress at 8.14%, which was 0.70% ahead of the planned schedule.