LAVIQ Sukhumvit 57 Construction Progress Update Q1/2018

0 5698

LAVIQ Construction Progress Q1/2018


The project was currently in the process of floor reinforcement and structural column reinforcement, structural concrete pouring, elevator wall concrete works for the building, 5th-floor works, 5B column works, stair works from 1M to 2A, and stair works from 1st floor to 2B.

The completed works included the 5B floor, stair works from 1st floor to 1M, ramp floor works for the car park from 4B to 5A, ramp floor works for the car park from 5A to 5B, and stair works from 1st floor to 2B.

According to the planned schedule, the project was expected to reach 7.44% completion.

At that time, the project had already reached 8.14% completion, which was 0.70% ahead of schedule.

LAVIQ Construction Progress Q1/2018

LAVIQ Construction Progress Q1/2018

LAVIQ Construction Progress Q1/2018

LAVIQ Construction Progress Q1/2018

LAVIQ Construction Progress Q1/2018

------------------------------------------
Explore more details about single detached homes, townhomes, home offices, and condominiums at:
Website : www.realasset.co.th
Facebook : www.facebook.com/RealAssetDevelopment
Instagram : www.instagram.com/realasset.development/
LINE@ : @realasset
Call Center : 1232